Free PUE Health Check
Section

Knowledge

Data Center Power Cable Labeling: Where NFPA 70E and TIA-606-C Meet

Data center power cable labeling runs on two separate standards: NFPA 70E arc-flash safety labels and ANSI/TIA-606-C circuit and cable identification labels. NFPA 70E ties a relabeling event to a change in the electrical distribution system, such as a new…

AI Data Center Water Usage: How It’s Actually Measured

US data centers consumed roughly 17.5 billion gallons of water directly in 2023, a figure projected to double or quadruple by 2028. Indirect water use from electricity generation typically makes up more than 80 percent of a facility’s total water…

Data Center Aisle Containment Is Commissioned Once, Then Assumed Forever

Summary: Data center aisle containment is one of the highest-return cooling upgrades an operator can deploy. Yet almost no facility re-measures its effectiveness after installation. Containment degrades over time as cables are added and moved, equipment swapped, and missing blanking panels…

How Liquid Cooling Data Center Retrofits Actually Work

Adding liquid cooling to an existing data center is primarily a facility infrastructure project: water loop capacity, power headroom, and floor loading, not a rack-level hardware swap. Most retrofits run air and liquid cooling side by side for an extended…

Total Power Usage Effectiveness: What PUE Misses on AI Racks

Total power usage effectiveness (TUE = ITUE x PUE) counts power lost inside IT equipment that standard PUE ignores. AI racks lose measurable power to fans, power supplies, and voltage regulator modules before it reaches the GPU die. Calculating TUE…

Data Center Water Leakage: Detection Is Reaching the Rack

Data center water leakage programs were built around raised-floor piping and CRAH units, not the cooling loop running through the rack. Direct liquid cooling and CDUs put leak points inside the rack, past where under-floor rope sensors are positioned to…

What Is the Right Server Room Temperature Range?

ASHRAE’s recommended envelope, 18 to 27 degrees Celsius, applies at the equipment air intake, not the room average. Allowable ranges widen from Class A1 to A4, so the ‘right’ upper limit depends on what hardware the room runs. Most facilities…

Data Center Temperature Sensor Placement: Where the Guides Stop Short

ASHRAE-based placement guidance is consistent on sensor counts and rack positions, but almost no published guide addresses what happens after installation. Calibration drift and single-point sensor failure are the two most common ways a correctly placed sensor grid quietly stops…